Description of Project: The scope of work is to construct 40mm thick asphaltic pavement carriageway of 6.0m wide with a surface dressed shoulder of 1.0m wide on both side of the road as well as construction of reinforced concrete lined drains and culverts at strategic built-up areas along the project road.
The works also include the construction of 1 No. 45 m long (3 nos. spans of 15m each) bridge with 11m total width comprising of 8m traffic way and 2 Nos. 1.5m wide elevated walkways. The bridge superstructure and substructure is made up of reinforced concrete and is founded on bored piles.
Client : CROSS RIVER STATE GOVERNMENT
Location of Project: Biase Local Government Area, River State
Project Cost (est.): BEME - Variable
Date Commissioned: August, 2010
Date Completed: In Progress